Back to news
Daily Market Briefing · 24 November 2026

Aurubis Delays Full Ramp-Up of Its $800 Million US Recycling Smelter

Furnace-suspension modifications will take about six months, lowering near-term throughput and pushing technical ramp-up into the second half of 2028.

A technical problem changes the schedule

Aurubis said components in the suspension systems of the top-blown rotary converters at its Richmond, Georgia plant must be modified. Replacement work across the furnaces is expected to take about six months, and the company now expects technical ramp-up in the second half of 2028. Throughput will remain below the original plan in the meantime, although Aurubis intends to continue purchasing feedstock for its wider smelter network. The company did not report a safety incident; it described the work as necessary for reliable long-term operation.[1][2]

Guidance falls below expectations

Aurubis forecast operating earnings before tax of €430–530 million for the financial year ending September 2027, below the €564 million average analyst expectation reported by Reuters. Richmond is expected to make a negative earnings contribution broadly comparable with the previous year. Preliminary operating pretax earnings for 2025–26 were €516 million, up from €355 million. The new range therefore reflects a combination of the delayed project contribution and a less favourable starting point than analysts had assumed, rather than a collapse in the established European operations.[1][2]

Why Richmond matters

The roughly $800 million facility is designed to process about 180,000 tonnes of complex recycling material annually and produce approximately 70,000 tonnes of blister copper. Aurubis describes it as the first US secondary smelter specializing in multimetal recycling. Its intended feed includes circuit boards, copper cable and other metal-bearing materials that have often been exported for processing. Successful ramp-up would therefore add domestic capacity for copper and other strategic metals; the delay postpones those supply-chain benefits as well as earnings.[3]

Commissioning risk is now visible

Greenfield metallurgical plants combine complex furnaces, material handling, emissions controls and variable feedstocks, so commissioning rarely resembles the steady-state model in an investment presentation. The disclosed component replacement gives a concrete cause and revised timetable, but it does not yet establish the final cost or the pace at which throughput will rise afterward. Aurubis had already described Richmond as being on an extended ramp-up in August. Investors and suppliers will now need evidence that the modifications solve the reliability constraint without creating additional bottlenecks.[1][3][4]

Sources & evidence

  1. Aurubis AG expects FY 2026/27 operating earnings before taxes below market expectations due to extended ramp-up of Richmond (opens in a new tab)
    Aurubis AGSource language en

    Official technical explanation, six-month modification period, revised ramp-up date and earnings guidance.

    Source note

    Issuer release accessible in full.

  2. Aurubis faces problems ramping up US plant, tempers expectations (opens in a new tab)
    Reuters via MarketScreenerSource language en

    Independent reporting on analyst expectations, prior-year earnings and the market interpretation.

    Source note

    Public Reuters republication; no paywall encountered.

  3. Environmental Protection at Richmond (opens in a new tab)
    Aurubis AGPublication date unconfirmedSource language en

    Facility investment, designed annual processing capacity and project background.

    Source note

    Undated corporate background page; capacity figures remain company projections.

  4. Aurubis moves full-year guidance to upper end of forecast range after notably improved Q3 (opens in a new tab)
    Aurubis AGSource language en

    Evidence that Richmond was already described as being in an extended ramp-up before the current modification announcement.

    Source note

    Issuer release accessible in full.